Questions about the extension?

Here are a few of the top questions we’re getting about the project extension:

What is the new timeline?

We’re extending the project by 6 months. We’ll launch Workday for WSU in January 2021. Here are the new dates:

March-August 2020 Complete system testing, report development, and training preparation

August-September 2020 User Acceptance Testing

October-December 2020 Training

January 2021 Start using Workday for WSU

January 2021-January 2022 Ongoing support

January 2022 and beyond Optimizing the system

Check out the updated Project Timeline page for a detailed list of activities.

Will this cost more money?

No, this extension will not increase the project budget.

Does this change the scope of the project?

No, the scope of the project will not change.

For answers to more frequently asked questions about the extension, check out the updated Project Timeline page, which we’ll continue to update based on community feedback.

Read the message from President Schulz and Vice President Stacy Pearson, and the story in the WSU Insider.