Issue: Duplication in Budget to Actuals reports

Known Issue: Initial Budget and Budget Amendment columns in Budget to Actuals reports are returning duplicate amendment entries.

Estimated Time to Resolution: April 16

Details: We identified an issue in the Budget to Actuals reports where the Initial Budget and Budget Amendment columns return duplicate amendment entries.

Several new budget amendment types were added to Workday after launch, and we discovered that they did not use the same logic as the Budget to Actuals reports. This led to amendments reporting in the wrong column, and in some cases in both the Initial Budget column and the Available Budget column. This caused the calculated columns for Current Budget and Total Budget fields to be doubled.

We are working on corrections and hope to have a solution in place by the end of next week.